Each of A, B, C and D need a unique time to do a certain work. A can do the work in x days and B can do the work in 2x days. A started the work and do it for 2229days then he is replaced by B, who completed remaining work in same time as C and D together can complete the whole work. The ratio of the efficiency of C and D is 4 : 5. If C and D work for alternative days starting from C then they can do the total work in 4412days.
What is the value of x?
6623
3313
1623
1427
The correct Answer is:B
To solve the problem step by step, let's break down the information given and derive the value of x.
Step 1: Determine the total work done by C and D
C and D work in the ratio of 4:5. If we let C's efficiency be 4k and D's efficiency be 5k, the total efficiency of C and D together is 4k+5k=9k.
Given that C and D can complete the work in 4412 days (which is 44.5 days), we can calculate the total work:
Total Work=Efficiency×Time=9k×44.5
Calculating 9×44.5:
9×44.5=400.5k
Thus, the total work W=400.5k.
Step 2: Calculate the work done by A
A can complete the work in x days, so A's efficiency is Wx.
A works for 2229 days (which is 2009 days). The work done by A is:
Work done by A=Efficiency×Time=Wx×2009
Substituting W=400.5k:
Work done by A=400.5kx×2009=80010k9x
Step 3: Calculate the remaining work
The remaining work after A has worked is:
Remaining Work=W−Work done by A=400.5k−80010k9x
Step 4: Calculate the work done by B
B completes the remaining work in the same time that C and D together can complete the whole work. Since C and D can complete the work in 44.5 days, B's work time is also 44.5 days.
B's efficiency is W2x. Thus, the work done by B is:
Work done by B=W2x×44.5=400.5k2x×44.5=400.5×44.5k2x
Step 5: Set up the equation
Since the remaining work done by B equals the remaining work calculated earlier, we can set up the equation:
400.5k−80010k9x=400.5×44.5k2x
Step 6: Simplify the equation
Dividing through by k (assuming k≠0):
400.5−800109x=400.5×44.52x
Step 7: Solve for x
Multiply through by 18x to eliminate the fractions:
18x×400.5−1600200=9×400.5×44.5
Calculating 9×400.5×44.5:
9×400.5×44.5=160020
Thus, we have:
7215x−1600200=160020
Combining like terms:
7215x=160020+1600200
7215x=1760220
Finally, solving for x:
x=17602207215=244.5
Conclusion
The value of x is 3313 days.
C and D work in the ratio of 4:5. If we let C's efficiency be 4k and D's efficiency be 5k, the total efficiency of C and D together is 4k+5k=9k.
A can complete the work in x days, so A's efficiency is Wx.
The remaining work after A has worked is:
B completes the remaining work in the same time that C and D together can complete the whole work. Since C and D can complete the work in 44.5 days, B's work time is also 44.5 days.
Since the remaining work done by B equals the remaining work calculated earlier, we can set up the equation:
Dividing through by k (assuming k≠0):
Multiply through by 18x to eliminate the fractions:
7215x=1760220
The value of x is 3313 days.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A can do a work in x days and B can do the same work in y days. If x>y , then who can do more work in 6 days?
View SolutionA can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View Solution
Knowledge Check
- Question 1 - Select One
Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A66(2/3)B33(1/3)C16(2/3)D14(2/7) - Question 2 - Select One
Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for 2229 days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is 4:5. If C and D work for
alternative days starting form C then they can do the total work
in 4412 days.A6623B3313C1623D1427 - Question 3 - Select One
A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
A12 daysB9 daysC10 daysD8 days
A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View SolutionA can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
View SolutionA can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
View SolutionA can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?
View SolutionA can do a piece of work in 10 days and B can dothe same piece of work in 20 days. They start the work together but after 5 days A leaves off. B will do the remaining piece of work in..
View Solution