A and B together can do a piece of work in 48 days and B & C together do the same work in 36 days. If first 24 day A work alone next 36 days B work alone and remaining work complete by C in 20 days, then find in how many days A and C complete work together?
2745days
2245days
2545days
2845days
To solve the problem step by step, we will break it down into manageable parts:
Step 1: Determine the total work
A and B together can complete the work in 48 days, and B and C can complete it in 36 days. We can find the total work using the least common multiple (LCM) of these two times.
- LCM of 48 and 36 = 144
Thus, the total work is 144 units.
Step 2: Calculate the efficiencies of A + B and B + C
Using the total work, we can find the efficiencies of A + B and B + C.
- Efficiency of A + B = Total Work / Time taken by A + B = 144 / 48 = 3 units/day
- Efficiency of B + C = Total Work / Time taken by B + C = 144 / 36 = 4 units/day
Step 3: Calculate the work done by A, B, and C
Now we will analyze the work done by A, B, and C over the specified days.
1. A works alone for 24 days:
- Let the efficiency of A be a.
- Work done by A in 24 days = 24a
2. B works alone for 36 days:
- Let the efficiency of B be b.
- Work done by B in 36 days = 36b
3. C works alone for 20 days:
- Let the efficiency of C be c.
- Work done by C in 20 days = 20c
Step 4: Set up equations based on the efficiencies
From the previous steps, we have:
- a+b=3 (from A + B)
- b+c=4 (from B + C)
Step 5: Calculate the total work done
Now we can calculate the total work done by A, B, and C:
- Total work done = Work done by A + Work done by B + Work done by C
- 24a+36b+20c=144
Step 6: Substitute and solve for efficiencies
Using the equations from Step 4:
1. From a+b=3, we can express a as a=3−b.
2. Substitute a into the total work equation:
24(3−b)+36b+20c=144
Simplifying gives:
72−24b+36b+20c=144
12b+20c=72
3b+5c=18(Equation 1)
3. From b+c=4, we can express c as c=4−b.
4. Substitute c into Equation 1:
3b+5(4−b)=18
Simplifying gives:
3b+20−5b=18
−2b+20=18
−2b=−2⇒b=1
5. Substitute b=1 back to find c:
c=4−b=4−1=3
6. Substitute b=1 into a+b=3:
a=3−1=2
Step 7: Calculate the efficiency of A and C together
Now we have:
- a=2
- b=1
- c=3
The efficiency of A + C:
A+C=a+c=2+3=5 units/day
Step 8: Calculate the time taken by A and C to complete the work together
Using the total work and their combined efficiency:
Time=Total WorkEfficiency of A + C=1445=28.8 days=2845 days
Final Answer
Thus, A and C together can complete the work in 28 days and 4/5 of a day.
---
A and B together can complete the work in 48 days, and B and C can complete it in 36 days. We can find the total work using the least common multiple (LCM) of these two times.
Using the total work, we can find the efficiencies of A + B and B + C.
- Efficiency of B + C = Total Work / Time taken by B + C = 144 / 36 = 4 units/day
Now we will analyze the work done by A, B, and C over the specified days.
- Let the efficiency of A be a.
- Work done by A in 24 days = 24a
- Let the efficiency of B be b.
- Work done by B in 36 days = 36b
- Let the efficiency of C be c.
- Work done by C in 20 days = 20c
From the previous steps, we have:
- b+c=4 (from B + C)
Now we can calculate the total work done by A, B, and C:
- 24a+36b+20c=144
Using the equations from Step 4:
2. Substitute a into the total work equation:
24(3−b)+36b+20c=144
Simplifying gives:
72−24b+36b+20c=144
12b+20c=72
3b+5c=18(Equation 1)
4. Substitute c into Equation 1:
3b+5(4−b)=18
Simplifying gives:
3b+20−5b=18
−2b+20=18
−2b=−2⇒b=1
c=4−b=4−1=3
a=3−1=2
Now we have:
- a=2
- b=1
- c=3
A+C=a+c=2+3=5 units/day
Using the total work and their combined efficiency:
Time=Total WorkEfficiency of A + C=1445=28.8 days=2845 days
Thus, A and C together can complete the work in 28 days and 4/5 of a day.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View SolutionA and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View Solution
Knowledge Check
Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42A and B together can do a piece of work in 5 days and A alone can do it in 8 days. B alone can do the same piece of work in:
A1113 daysB1313 daysC1645 daysD1235 days
A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionA and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
View SolutionA can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
View SolutionX alone can do a piece of work in 12 days and Y alone can do the same work in 6 days. In how many days will both together complete the same work?
View Solution