Doubtnut Promotions Sticky

If P can do a work in 6 days and Q Can do the same work in
8 days. R can do the same work in 12 days. If they are
woeking together then the work will be completed in how
many days?

A

73days

B

83days

C

103days

D

113days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(b)


To solve the problem of how many days P, Q, and R will take to complete the work together, we can follow these steps:

Step 1: Determine the work rates of P, Q, and R
- P can complete the work in 6 days, so P's work rate is 16 of the work per day.
- Q can complete the work in 8 days, so Q's work rate is 18 of the work per day.
- R can complete the work in 12 days, so R's work rate is 112 of the work per day.

Step 2: Find a common denominator
To add the work rates, we need a common denominator. The least common multiple (LCM) of 6, 8, and 12 is 24.

Step 3: Convert each work rate to the common denominator
- For P: 16=424
- For Q: 18=324
- For R: 112=224

Step 4: Add the work rates together
Now, we can add the work rates:
Total work rate=424+324+224=924

Step 5: Simplify the total work rate
The total work rate can be simplified:
924=38
This means together, they can complete 38 of the work in one day.

Step 6: Calculate the time taken to complete the work
To find out how many days it will take to complete the entire work, we take the reciprocal of the total work rate:
Time taken=138=83 days

Final Answer
Thus, P, Q, and R together will complete the work in 83 days, which is approximately 2.67 days or 2 days and 8 hours.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?

    A12
    B10
    C15
    D24
  • Question 2 - Select One

    A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?

    A12 days
    B8 days
    C9 days
    D1012 days
  • Question 3 - Select One

    A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?

    A15
    B16
    C10
    D12